Most multi-site programs report one number: percent complete. It sounds clear, but it hides almost everything that matters.
A high percent complete could mean on track, or it could mean the easy sites are done and the hard ones are stuck. It doesn't say how many sites need a revisit, which contractor is slipping, or whether the work done has been billed.
The right project management KPIs for multi-site work cover three areas at once: delivery, quality and money. Track only one and you'll be surprised by the other two. Below are seven KPIs, grouped into those three areas.
Delivery KPIs Show Whether You'll Finish on Time, Not Just How Much Is Done
1. Ticket completion rate
Completed tickets divided by total tickets, tracked weekly. The trend matters more than the number. Compare your weekly pace with the pace needed to hit the deadline, and you'll see a slip today, not at the deadline.
2. Average time to close
Days from ticket assignment to completion. A rising average is often the first sign of a contractor capacity problem or a blocked step, such as a slow data review.
3. Status distribution
How many tickets sit in each stage: Assigned, Data Review, Site Validated, Revisit Needed, Completed. A pile-up in one stage shows exactly where the bottleneck is.
Quality KPIs Catch Revisits Before They Eat Your Margin
4. Revisit rate (the inverse of first-time fix rate)
The share of sites that needed a second visit. Industry surveys put the average first-time fix rate around 75%, which means one in four visits needs a return trip. Each truck roll typically costs $200–$300 or more, and PTC reports a failed first visit needs about 1.6 more dispatches.
5. Contractor performance
Completion rate, time to close and revisit rate, broken down by contractor. This turns gut feeling into facts and shows who should get more work. Platforms like ServiceChannel have made contractor scorecards standard in facilities management for this reason.
Financial KPIs Must Update When the Work Does, Not at Month-End
6. Revenue earned vs target
Revenue from completed tickets compared with the program's total value. If percent complete is well ahead of percent of revenue earned, the remaining sites are more valuable, or something is mispriced.
7. Fees and billing status
Contractor fees owed, and how much completed work has been billed. Unbilled completed work is cash you've earned but can't use. Project financial tracking should show this per project and per contractor, updated as tickets close.
In ClickPM, revenue, fees and billing sit on the same dashboard as ticket status, filtered by project or contractor, so finance and operations read the same numbers.
Evidence in Practice
Published field service benchmarks show why these KPIs matter:
First-time fix rate: Industry surveys put the average near 75%. Top performers hold it above 85%.
Extra dispatches: PTC reports a call not resolved on the first visit needs about 1.6 more dispatches.
Extra effort: Vsight notes that a failed first visit roughly triples the field effort on that job.
Annual cost: Fieldproxy's worked example shows that at 100 jobs a week, a 75% first-time fix rate means 25 return visits weekly, about $260,000 a year at $200 per visit.
Measurement window: Aquant recommends measuring repeat visits over 30 days, so related returns aren't split into new tickets.
These are the numbers that percent complete hides.
What This Means for Multi-Site Project Managers
Report three numbers, not one. At minimum: completion rate, revisit rate and revenue earned vs target.
Break every KPI down by contractor. Averages hide your best and worst performers.
Watch the status stages, not just "done." The bottleneck is usually in the middle.
Fix revisits at the source. See how to reduce revisits and get field work done right the first time.
Cut drive time to lift completion rate. Read our route optimization guide.
Frequently Asked Questions
What are the most important project management KPIs?
For multi-site work: completion rate, time to close, status distribution, revisit rate, contractor performance, revenue vs target, and fees and billing status.
What is a good first-time fix rate?
Industry averages sit around 75%. Top performers stay above 85%.
Sources
PTC, "What is First-Time Fix Rate?" — www.ptc.com
Vsight, "What is First Time Fix Rate (FTFR)?" — vsight.io
XOi, truck roll cost — www.xoi.io
ServiceChannel, contractor scorecard (press) — servicechannel.com
Fieldproxy, first-time fix rate guide — www.fieldproxy.ai
We built ClickPM so completed tickets, revenue, fees and billing all update together, and you can filter by project or contractor in seconds.